Handbook / The document set
Submittals
Shop drawings, samples and product data, tracked through review so a long-lead order is not placed on an unapproved detail.
A submittal carries a revision number, a lead time and a required-on-site date. That combination is what tells you when a review has stopped being a formality and started being the thing that will delay the job.
Draft→Submitted→Under review→Approved
A submittal
Returning one revise and resubmit starts the next revision rather than editing the old one, so the review history of a detail is readable end to end.
Undoing things
| What happened | The way back |
|---|---|
| Reviewed with the wrong outcome | Review it again; the latest decision stands and the previous one stays in the history. |
| Submitted too early | Put it back to draft. |
| Wrong revision | Each revision is its own record. Void the wrong one. |
Access: Document management.